CIC Data Base Inquiry
Reference No. 138
2000-2002 Audi TT Coupe/Roadster
R&R or R&I Rocker Molding
 

Date of Request: April 20, 2002
Original Date Posted: May 30, 2002

Data Providers:
MOTOR Information Services, ADP Claims Solutions Group


Issue:

The time allowance is insufficient due to the additional time required to remove the excessive rubberized gravel-guard/undercoating that impedes access to the 8 torque bolts that retain the molding. The rubberized undercoating not only covers up the location of the torque bolts, but must also be meticulously removed from the torque bolt grooves so the torque tool can fit into the bold head.

Mitchell is the only data provider that recognizes that the Scuff Plate (#8N0 853 492 E 01C) must also be removed to facilitate the removal of the rocker molding and also states the Scuff-Plate is a non-reusable component and must be replaces when the rocker molding is removed or replaced.
 

Suggestion:

To all providers: 

1. Time should be increased to 1.2 hours per rocker molding and/or a "labor note" added to inform the estimator of the impediment problem to the torque bolts.

2. The "labor note" should also inform the estimator the Scuff-Plate replacement requirement. 

3. And should also remind estimator that rubberized material must be replaced.

Results:

Mitchell

 

Original Time Allowance

.6 Hours

Labor Note: Includes R&R (Non-Reusable Part) Scuff Plate

 

Response: The allowance to R&I/R&R the Rocker Panel molding does not include the removal or application of Anti-Corrosion rust resistant material, i.e. undercoating. Reference to this subject can be found on Page P3 of the Procedure pages under the Additions to Labor Times column.

 

MOTOR

 

Original Time Allowance

.4 Hours

Labor Note: None

 

Adjusted Time Allowance

1.4 hours

Labor Note: Includes R&R (Non-Reusable Part) Sill Plate and Removal of Stone Guard at Bolts' head as needed.

 

ADP

 

Original Time Allowance

Not Presently Known

Labor Note: None

 

Adjusted Time Allowance

1.0 Hours

Labor Note: Each rocker molding.

     Back to DB Inquiries List      Estimating Committee Page